Realizations
Aliplast Sp. z o.o. anodizing
Lublin
Category of facility | Warehouses | |
---|---|---|
The total area of | 6.348 m2 | |
Implementation year | 2017 |
The scope of work performed by the MCM Project:
- Detailed design of the hall structure with crane beams - above-ground part
- Execution, delivery and assembly of reinforced concrete columns for the hall
- Execution, delivery and assembly of steel hall structure
- Delivery and assembly of roof cladding and hall walls
- Delivery and assembly of hall equipment (roof skylights, industrial gates, roof belayers)
- Construction of partition walls in the hall
- As-built documentation of the hall