Production hall with office in Pomeranian voivodeship
woj. pomorskie
Category of facility | Production halls | |
---|---|---|
Type of hall | Production hall | |
The total area of | 3335 m2 | |
Implementation year | 2020 |
The scope of work performer by the MCM Project:
a) the scope of executive design:
- foundations of the hall and office building
- structure of the hall
- structure of the office building
- roofing and wall cladding
b) the scope of work:
- earthworks
- buildings foundations
- execution, delivery and assembly of hall structure
- delivery and assembly of crane beams
- delivery and assembly of roofing and wall cladding
- delivery and assembly of hall equipment (gates, windows, doors, skylights, cranes)
- concrete flooring inside the hall
- construction and finishing works of office building
- land use
- internal and external electrical installations
- internal and External sanitary installations
- post-completion documentation