Realizations
SSC Sp. z o.o. 2
Mielec
Category of facility | Warehouses | |
---|---|---|
Type of hall | Production and storage hall | |
Industry | Gastronomy equipment | |
The total area of | 2.231 m2 | |
Implementation year | 2017 |
The scope of work performed by the MCM Project:
- Construction and executive design of the steel structure of the hall and foundations
- Preparation of prefabricated steel hall structure elements with casing and thermal insulation of the roof and walls
- Delivery of all elements to the construction site together with their unloading
- Assembly of the hall structure together with the casing
- Provision of cranes, complete assembly equipment, scaffolding and all auxiliary materials for assembly of the hall
- Preparation of as-built documentation