Realizations
FTSH Mielczarek Andrzej
Zduńska Wola
Category of facility | Warehouses | |
---|---|---|
The total area of | 1.440 m2 | |
Implementation year | 2019 |
The scope of work performed by the MCM Project:
a) execution of an executive design in the field of:
- design of hall foundations
- steel structure design of the hall with housing
b) performance of works in the scope of:
- earthworks for hall and floor foundations
- hall foundations
- hall in steel structure
- foundations for the B10 concrete floor, 10 cm thick
- B30 concrete floor slab, 15 cm thick, with dispersed reinforcement, smoothly seized with expansion joints
- as-built documentation