Realizations
markARTUR
Lublin
Category of facility | Warehouses | |
---|---|---|
The total area of | 3.025 m2 | |
Implementation year | 2019 |
The scope of work performed by the MCM Project:
a) drawing up the executive design of the roof cladding, external and internal wall cladding
b) performance of works in the scope of:
- delivery and assembly of steel structure
- delivery and assembly of roof cladding and hall walls
- delivery and assembly of loading docks, gates, doors and smoke vents
- making a partition wall and smoke curtains
- delivery and assembly of gates in an office building
- post-completion documentation