Realizations
Łódzkie Zakłady Metalowe LOZAMET Sp. z o.o.
Łódź
Category of facility | Warehouses | |
---|---|---|
The total area of | 1.200 m2 | |
Implementation year | 2018 |
The scope of work performed by the MCM Project:
- Performing earthworks for the hall
- Construction of hall foundations
- Execution, delivery and assembly of steel hall structure
- Delivery and assembly of roof cladding and hall walls
- Delivery and assembly of hall equipment (gates, windows, doors and skylights)
- Construction of an industrial floor in the hall
- Adaptation of the existing gable wall to fire resistance REI60
- Performance of storm water drainage and sanitary installations
- Disassembly and demolition
- Performance of maneuvering areas
- Foundations for external shelving
- Central heating installation and ventilation in the hall
- Electrical installation in the hall + facade lighting fixtures
- As-built documentation of the hall