MPC METAL SP. Z O.O.
Lublin
Category of facility | Production and storage halls | |
---|---|---|
The total area of | 2.275 m2 | |
Implementation year | 2011 |
Between October and December 2011 MCM Project Sp z o.o. located in Łódź at 12 Piłsudskiego Street was the general contractor of the production steel hall of the total space of 1.890 square meters and a warehouse of the space of 170 square meters
The scope of work consisted of delivery and assembling the steel hall construction and assembling the walls and roof of the hall.
MCM Project built the hall according to the agreed schedule and in line with all technical requirements. The staff was fully dedicated to the project and very professional.
It is worth mentioning that they were very well organized and have been proactive in assisting us in resolving any construction matters raised. They were flexible and helpful and paid attention to the invertor’s needs and requirements.
We therefore have no hesitation in recommending MCM Project as a reliable, professional and ambitious partner in steel hall constructing.